Eastern New Mexico Connector Transmission Line Project

Eastern New Mexico Connector Transmission Line Project Details


Project Scope
  • Transmission Line: 278 miles, double-circuit, up to 500 kV alternating current (AC) line
Capacity
  • 3,200 MW, enough to power more than 1 million homes
Investment
  • RETA and Eastern New Mexico Connector LLC are co-developers of the project
  • Lease agreement was approved in December 2025
Economic Benefit
  • Increased employment
  • Income to landowners
  • Connection between PNM’s Blackwater, Taiban Mesa, Hidden Mountain and Pajarito Substations, incorporating wind and/or solar energy sources into the grid

 

About the Eastern New Mexico Connector Transmission Line Project

RETA has entered into a development and lease agreement with Eastern New Mexico Connector LLC for co-development of the Eastern New Mexico Connector Transmission Project, which offers 278 miles of alternating current (AC) transmission line rated to carry up to 3,200 MW.

The project will be built in five stages and, once constructed, will be able to transmit renewable energy, including wind, solar and battery storage to customers and markets in New Mexico and across the southwestern United States.

The anticipated connection date of the new renewable energy sources is 2032.

ENMC

A Special NM RETA Board of Directors meeting will be held on Monday, September 14, 2026 at 2:30 pm via ZOOM. For more information